PADDLE STEAMER WAVERLEY

HERITAGE REBUILD DIARY

Supported by and

Summary Work Programme as at 29 July 2000

Please note that the following is a simplified summary showing some key elements from the detailed programme.

Ship berthed and de-stored Complete
Sponsons and paddles and shafts removed Complete
Boiler removed Complete
Engine dismantled and auxiliaries removed Complete
Aft passenger accommodation stripped Complete
Galley stripped Complete
Drydocking for blasting and steel renewals Complete
New Sponsons fabricated. Complete
New Sponsons attached Complete
Wheels and Shafts re-fitted and Running Gear assembled Complete
New Boilers installed Complete
Boileroom Pipework 95% Complete
Raise Steam 3rd to 5th August 2000
Funnels fabricated Complete
Funnels fitted As planned on 24th July 2000
Dining Saloon outfit complete 7th August 2000
Lower Bar and Lower Dining Saloon outfit 7th August 2000
Inclining Test 2nd August 2000
Quayside Trials 9th August 2000
Sea Trials 12th - 13th August 2000
Commissioning complete 14th August 2000
Ship handover 15th August 2000
Arrival in Glasgow and re-entry into service 18th August 2000

PROGRESS REPORTS

29 November 1999

Waverley Steam Navigation Co Ltd announced that the contract for the Heritage Rebuild had been awarded to George Prior Engineering Ltd of Great Yarmouth.

Press Release.

18 - 21 December 1999 P.S. Waverley sails from temporary lay-up at Avonmouth to Great Yarmouth.

An account of her voyage.

9 January 2000 Preparatory work under way.
11 January 2000 Funnels and paddle wheels being dismantled.
14 January 2000 Both funnels removed
17 January 2000 Sponsons being dismantled
18 January 2000 Main engine crankshaft removed
24 January 2000 Paddle wheels ashore
25 January 2000 Boiler out
27 January 2000 New boilers and empty boiler room
1 February 2000 Cleaning up in progress
8 February 2000 Dining Saloon and Engine and Boiler Rooms stripped
16 February 2000 In Dry-dock
24 February 2000 New Sponson Houses under Construction
29 February 2000 Report on Progress to Date
1 March 2000 Steelwork renewals in Boileroom
8 March 2000 More Steelwork Renewals
14 March 2000 Around the Workshop and Dry Dock
15 March 2000 News from North of the Border
15 March 2000 Refurbishment of Main Engine
22 March 2000 Sponson delivered and some interesting riveting
23 March 2000 Pump refurbishment in progress in Scotland
4 April 2000 Reconstructing the Boileroom, Bar and Dining Saloon
13 April 2000 Final work in Dry Dock
18 April 2000 Some more snaps from Waverley HQ
20 April 2000 Leaving Dry Dock
27 April 2000 Port paddle wing block bearing housing
28 April 2000 New starboard sponson house being fitted - new after deck shelter being fabricated
29 April 2000 PSPS Visit to George Prior Engineering
10 May 2000 Aerial View
11 May 2000 Movement of new boilers announced
15 May 2000 Crankshaft polishing in progress
16 May 2000 Boilers Delivered
26 May 2000 Boilers lowered into Position
3 June 2000 Second PSPS Visit to Great Yarmouth
4 June 2000 June Progress Report
5 June 2000 Progress all round the ship
7 June 2000 Main Engine crankshaft refitted
20 June 2000 Fitting out around the ship
  Main Engine re-assembly
5 July 2000 Paddle wheels ready - interior fit started
  Paddle wheel refitted - fiddley in place
  Funnels under construction
21 July 2000 Ian McMillan, Project Director, said "There is a lot of work still to be done, but nobody has said to me it won't be done on time and I'm not expecting them to."
24 July 2000 Funnels Fitted
27 July 2000 Engine Room Interior - Funnels in Place - Management Team
29 July 2000 Views from across the River Yare
2 August 2000 The Inclining Test
7 August 2000 Crew Assembling
11 August 2000 Almost ready to sail!
12 August 2000 Sea Trials
15 August 2000 Group Photographs at George Prior's
16 August 2000 Waverley Sails from Great Yarmouth
Chief Photographer and Project Manager Gordon Reid stands beneath Waverley's paddle wheels.

Picture by Nick James